Showing posts with label San Andreas Pipeline No.3 Installation. Show all posts
Showing posts with label San Andreas Pipeline No.3 Installation. Show all posts

Wednesday, January 6, 2010

Construction resumes in the Merced Manor Neighborhood





Mountain Cascade, Inc. contractor working for the SFPUC on the San Andreas Piepline No. 3 will begin the 36" water pipeline installation on Eucalyptus Drive. Construction will be ongoing throughout January.

The installation will continue in February along Eucalyptus Drive through 22nd Avenue to Sloat Boulevard.

Work hours are Monday through Friday from 7 a.m. - 5 p.m.

For more information on this project, please visit www.sfwater.org/sanandreas3




Monday, November 30, 2009

Minor Traffic Impact on Thomas More Way


Today crews will begin pipeline excavation for the San Andreas Pipeline No.3 Installation project along Thomas More Way through the San Francisco Golf Club. A minor traffic deviation will take place on Thomas More Way, specially in front of Saint Thomas More Catholic School. The deviation is scheduled to impact commuters this week only.
We are working with the school and other nearby institutions to minimize disruptions.


For more information on San Andreas Pipeline No.3 Installation, please visit www.sfwater.org/sanandreas3

Friday, October 23, 2009

San Andreas Pipeline No. 3 Installation In Full Construction

The pipeline installation mobilized this week at the intersection of Thomas More Way and Brotherhood Way. Crews will be crossing under this intersection on Monday, October 26th and will continue to Crespi Drive. SFPUC and Mountain Cascade, Inc. have coordinated efforts with Saint Thomas More Catholic School and Church and other nearby institutions in this area to minimize disruptions.

There will be continuous construction at the Crespi Drive round about circle accompanied by a bit that will be dug under Holloway Avenue to 19th Avenue.

Crews are also preparing to dig an additional bore pit at the intersection of 19th Avenue and Eucalyptus Drive. To comply with the City’s holiday construction moratorium, crews will cease construction in this area between the week of November 23, 2009 through the week of January 4, 2010. Construction will reconvene in mid-January 2010, with crews continuing to dig under Eucalyptus Drive to Merced Manor Reservoir.

Let us know how we can minimize disruptions or inconvenience. We look forward to working with you.

Workdays & Hours
Monday – Friday 7:00 A.M. – 5:00 P.M.
No construction will occur outside of these posted hours without advanced written notice.

More Information
Look for continuing updates about this project here.