Thursday, March 11, 2010

New Mt Davidson Pump Station Nears Completion

The Mt Davidson Pump Station project team are making the final touches on the new, modern and efficient water pumping station located on Agua Way at La Bica.

The new building was designed to look like homes in the neighborhood and its new pumps and electrical equipment are modern and more energy efficient.

New landscaping is beginning to grow and bloom on the La Bica Path and surrounding the upgraded Stanford Heights Reservoir. New plants will be added in front of the pump station building soon.

Tuesday, March 9, 2010

Update: Eucalyptus and 19th Avenue in San Francisco

A contractor’s crew is beginning to dig a trench to install 36” diameter steel water pipe just west of the existing bore pit located at the intersection of Eucalyptus and 19th Avenue in San Francisco. The crew will be heading westbound along Eucalyptus to 22nd Avenue to install the water pipe. Later this spring, the installation will turn northbound up 22nd Avenue, terminating near Sloat Blvd. at the Merced Manor Reservoir.

Neighbors can expect some parking limitations, with 72 hours notification before any removal of parking. Iris Martin Lopez has been working with the nearby schools and the YMCA to ensure that daily routines are not obstructed. She can be reached at (415) 554-3222 or via email: ilopez@sfwater.org.

Rain temporarily halted work on Junipero Serra and Holloway, but workers will return this week as weather improves. Weather permitting, the contractor plans to complete work at that location by early April.

Thursday, March 4, 2010

Public Comment Welcome on Agua Way Bamboo Plan


Our landscape folks have created a proposed planting plan for the area near the blue valves and chlorine building along Agua Way near Teresita. The plan includes beautiful clumping bamboo and blooming flowers that will create a 'green screen' that neighbors can enjoy instead of viewing the valves and other equipment.
You can view the drawings near the valves on Agua Way.
Please provide comments by noon on Thursday, March 11th via email to asinclair@sfwater.org.
We will soon be painting the chlorine building, DPW will repave Agua Way this Spring and then we can plant proposed bamboo and flowers. Bamboo can grow between 12 and 16 feet in height and will fill out over time.
Thank you to the many Agua Way neighbors who suggested bamboo as a good option for everyone.

Wednesday, February 24, 2010

Junipero Serra and Holloway Update

As weather permits, construction crews are continuing open trench work to install a water pipeline along Junipero Serra Blvd. at Holloway in San Francisco. Currently, the south-bound lane on the left-hand side of the boulevard is closed to traffic, but well placed markings and traffic signage have kept cars moving smoothly.

Regular work hours are Monday to Friday, 9 a.m. to 4 p.m. We welcome your input on how we can minimize inconvenience and disruption near your home or business. Please contact Iris Martin Lopez at SFPUC Communications at (415) 554-3222 or ilopez@sfwater.org. In addition to subscribing to this blog for updates, you can follow the progress of the San Andreas Pipeline #3 replacement on Twitter at www.twitter/SAPL3.

Wildflowers Coming This Spring near Palo Alto Ave


This Spring, watch for colorful ,beautiful wildflowers on the Water Dept property near the intersection of Palo Alto Ave and Marview in the Twin Peaks area.




The area was recently "hydroseeded" as part of a restoration project requested by neighbors after the completion of the Palo Alto Pump Station. Hydroseeding often looks like paint at first - it is usually bright green or blue - and the concentrated seed mix germinates and blooms with rain or moisture.




We would love to see some photos from neighbors posted on this blog!

Wednesday, February 10, 2010

Construction Update on Junipero Serra and Holloway Avenue in San Francisco

In anticipation of more rain this Friday, the construction crew at Junipero Serra and Holloway Avenue will finish securing and plating the trench today and will re-open the westbound lane of Holloway Avenue to traffic.

The team will resume work on the trench beginning Tuesday, February 16th, and for safety reasons must close the western-most (southbound) lane of Junipero Serra Blvd. until the work is completed. The SFPUC contractor will work extended hours on Tuesday and Wednesday in order to minimize the number of evenings that drivers will be inconvenienced along Junipero Serra.

We will post frequent updates to keep neighbors and commuters informed throughout the project. Please subscribe to this blog or sign up to follow us on twitter at www.twitter/SAPL3 for regular construction updates in your neighborhood.

If you have any comments or questions about the project, please contact Iris Martin Lopez at SFPUC Communications at (415) 554-3222.

Iris Martin Lopez
Communications Liaison, San Andreas Pipeline No. 3
415-554-3222
Email: ilopez@sfwater.org
24 hours: (415) 334-4007

Tuesday, February 9, 2010

Emergency Repairs at Junipero Serra and Holloway

A construction crew will be working through the night to reinforce the street at the intersection of Junipero Serra Boulevard and Holloway Avenue. To avoid a potential safety hazard for both motorists and pedestrians, crews will work on this area until it is safely repaired.

Additional police will be assigned to direct traffic at the intersection, and the westbound lane of Holloway Avenue has been closed to motorists until further notice. The SFPUC contractor is completing a drinking water pipeline installation and backfilling the trench at this location.

Please subscribe to this blog for regular construction updates in your neighborhood. If you have any comments or questions about the project, please contact Iris Martin Lopez at SFPUC Communications at (415) 554-3222.

Friday, January 15, 2010

Snow Fence Added to Protect Plants at Stanford Heights Reservoir


Residents may notice snow fencing around the perimeter of Stanford Heights Reservoir this week. The temporary fence was added in order to protect the new landscaping recently installed and allow it to grow.
The fence will remain in place until the new plants and flowers have a chance to grow. It will be removed once the landscape team feel the plants are safe from damage.

Tragic Earthquake in Haiti a Shocking Reminder to Store Water and Be Prepared

The devastating and tragic 7.0 earthquake in Haiti on January 12th is a shocking reminder for all of us to be prepared for a major earthquake to strike the San Francisco Bay Area at any time.

Store at least one gallon of water per person per day to last at least three days after a major disaster. Store additional water for houseguests and pets. Store water away from sunlight and heat and replace every six months. Learn more about getting prepared by visiting http://www.72hours.org/.

Wednesday, January 13, 2010

Watch for Wildflowers this Spring at Summit Reservoir

Watch for wildflowers at Summit Reservoir, located near the intersection of Palo Alto Ave and Marview in the Twin Peaks area. Our SFPUC gardener recently cast a mix of colorful wildflowers along the hillside near Palo Alto Ave.

The SFPUC also plans to "hydroseed" the area this Spring as part of a restoration project requested by neighbors after the completion of the Palo Alto Pump Station. Hydroseeding often looks like paint at first - it is usually bright green or blue - and the concentrated seed mix germinates and blooms with rain or moisture. Watch for the hydroseeding this Spring.