Monday, June 29, 2009

Fence Installation Beginning this Summer

Installation of the new security fence around Stanford Heights Reservoir is beginning! New fence posts can be seen along Agua Way. It will be a 10 foot high, black vinyl-clad fence surrounding the reservoir.

The east reservoir basin retrofit work is nearing completion and will be placed back in service in early fall.

Friday, June 12, 2009

New Fence and Landscaping Coming to Stanford Heights Reservoir


The countdown to completion of the Stanford Heights Reservoir Seismic Retrofit project is beginning!
In summer 2009, residents can expect to see a new 10 foot security fence installed around the perimeter. New landscaping will be installed in late July/August to beautify the area. Native wildflower and grass seeds will be adding using 'hydroseeding' and colorful native plants and bushes will be planted.
Project completion is expected fall 2009!